After a disaster, if the original primary becomes available again, you may want to revert the role of the Primary back to this host.
To restore the primary host
For Takeover with the Fast-failback option:
The original primary, after it has recovered, will be in the Acting as secondary state. If the original Primary is not in the Acting as secondary state, verify whether your network connection has been restored.
To synchronize this original Primary and the new Primary, use the Resynchronize Secondaries option from new Primary's context menu.
For Takeover without the Fast-failback option:
After performing a takeover without fast-failback, you must convert the original Primary to a Secondary by using the Make Secondary option.
After the Make Secondary operation, the original primary will be converted to a secondary. Right-click on this Secondary RVG and select Start Replication with the Synchronize Automatically option.
After the sychronization is complete, perform a migrate operation to transfer the primary role back to the original Primary. To do this, right-click on the Primary RVG and select Migrate from the menu that appears.